|
|
Packing
Procedures
The importance of correct installation of gland packing to achieve
satisfactory performance cannot be overemphasized. The following steps
outline these procedures:
- Shut
the system down, isolating the equipment to be packed. Flush the
system if required, and relieve internal equipment pressure. Disable
the motor to prevent accidental start-up. Use all safety equipment
required.
- Remove
all of the old packing from the stuffing box. Note the proper location
of the lantern ring (if one is used). Clean the stuffing box and shaft
thoroughly. Examine the shaft or shaft sleeve for excessive wear and
replace the shaft or sleeve if it is worn or scored. Test the bearings
and replace them if end play or whip is outside the equipment
manufacturer’s specifications or more than 0.01mm TIR. Check bearing
oil for contamination and change it and the oil seals if needed.
Examine the stuffing box carefully. Large corrosion pits of ‘blow
holes” in the casting can provide leak paths along the outside of
the packing set which can be impossible to seal without placing
excessive gland pressure on the packing set. This can cause premature
failure by eliminating the lubrication film under the packing. Fill
these pits with compatible epoxy or weld. Packing rings must not be
“hung up” by a stuffing box bore that is too rough.
- From
bulk packing, cut rings on a mandrel of the same diameter as the
shaft. Slide the rings off the mandrel. Keep the packing clean.
Remember that dirt on new packing reduces service life.
- Install
one ring at a time. Twist the ring sideways to open it enough to slip
over the shaft. Push each ring into the stuffing box individually
until it is seated. Stagger the ring joints keeping them at least 90
degrees apart. Install the lantern ring in the proper location within
the packing set.
- After
the last ring is installed. Draw the gland up evenly and tighten the
gland bolts Finger Tight only! Turn the pump shaft by hand to ensure
that there is no binding.
- Do
Not Start Dry! Turn on the seal water, enable motor, open the valves
and fold the pump cavity. Bleed air from the system.
- Start
the pump, allowing generous leakage, and take up on the gland bolts
gradually one flat at a time. Continue to take up on the gland bolts
until leakage is reduce to an acceptable level. Do not try to stop all
leakage! With the exception of a few styles in certain application, dry
running can glaze the packing set and cause packing failure. Remember
that pump packing should leak a little to work. Allowing a little more
leakage at start-up often multiples the packing service life.
|